Facility built in 2011, first revamped by Aktid in 2015.
Second revamping in 2025 to adapt to the new sorting guidelines extension, leading to: evolution of the incoming waste stream, technical adaptation of the process to the developing flow, and redesign of the flat materials line.
Modification of the existing core process within a constrained environment and complex access conditions.
Revamping carried out safely within a tight schedule: 13 weeks of shutdown.
Aktid-designed ballistic separator with cardboard extraction.
112 kb
Location :
Le Mans
Customer :
Suez for ValorPôle 72
Hourly Throughput :
From 10 to 13 t/h
Incoming waste :
Packaging materials stream adapted to the new sorting guidelines and extended material mix